How come the answer is (d) for the MCQ no. 2

Screenshot_20240414_000705.jpg

Shaviri Reddy

Shaviri Reddy

CA Inter

★ 1K+

14-Apr-24 00:08

694

Answers (3)

There is expected loss as well


CA Suraj Lakhotia

CA Suraj Lakhotia

Admin

15-Apr-24 19:23

Revenue = 28 lakhs Cost incurred = 30 lakhs So loss is 2 lakhs Total expected loss = 8 lakhs. 2 is already recognised, we need to recognise additional 6 lakhs. So total cost = 30 + 6 = 36