in the illustration (attached below) ,why the contract price was credited with 90+9. ? In video 4 AS -7 ,in the same illustration,the contract price was credited with reimbursable cost only(90000)

5585d9ff-c99c-4f0f-97fe-2776ce9d1f68.jpg
c2046157-1a3b-476d-bde3-d57327b91cad.jpg

venkatesh sundharamoorthy

venkatesh sundharamoorthy

CA Final

★ 34K+

17-Apr-21 10:00

719

Answers (1)

Best Answer

The solution in the study material is incorrect When the outcome of a construction contract cannot be estimated reliably: (a) revenue should be recognised only to the extent of contract costs incurred of which recovery is probable; and (b) contract costs should be recognised as an expense in the period in which they are incurred Here is the correct solution attached