"Outcome of the contract cannot be estimated" What does it mean? Does it mean that: the revenue from such cannot be measured?

Answers (1)

ruchi lahoti

ruchi lahoti

Moderator

18-Jul-20 11:40

Yes. Nevertheless, it may be probable that the enterprise will recover the contract costs incurred. Therefore, contract revenue is recognised only to the extent of costs incurred that are expected to be recovered.