Can you please explain how to solve qn 4 and 5 ?

IMG_20240501_184612.jpg
IMG_20240501_184606.jpg

Ramya Sundar

Ramya Sundar

CA Final

5K+

01-May-24 18:47

388

Answers (3)

Q.4 In this question the revenue to be recognised to the extent of work completed . Here it is given in question certified work completed =320 lakhs so the revenue to be recognised is 320 lakhs Q.5 In this question cost incurred till date is given as 360 lakhs. So expense is to be recognised to the extent of expense incurred so answer is 360 lakhs


Refer this

Attachments

27ace75c-334e-4185-9587-7596ecdf2f30.jpg

Sherli Njrs

Sherli Njrs

CA Final

5K+

01-May-24 20:47

Thank you so much!


Thread Starter

Ramya Sundar

Ramya Sundar

CA Final

5K+

01-May-24 21:41