How to compute the answer to point (iii)

IMG-20220520-WA0000.jpg

Subramanyam N

Subramanyam N

CA Inter

6K+

20-May-22 08:36

233

Answers (2)

Best Answer

No. of cakes - 605 and 50 units per batch No. of batches - 605/50 = 12.1 Here Direct materials are the variable costs and are calculated partly as Rs 5000 * 12.1 But the Whole Fixed costs should be incurred even if one unit in the batch is produced So , we have to take the whole batch of 13 instead of 12.1 Hence The fixed costs - Direct wages and Oven set up costs are calculated for 13 batches Hope it's clear

IMG20220520122254.jpg

Avasarala Vivek Aditya

Avasarala Vivek Aditya

CA Inter

6K+

20-May-22 12:28

How come the answer has changed ? I got 186.26 as the answer.


Avasarala Vivek Aditya

Avasarala Vivek Aditya

CA Inter

6K+

20-May-22 11:42