Could anyone explain the second point which are given under the head of effect of anticipatory breach
Answers (4)
Best Answer
The promisee can treat the contract is on- going (ie, not ended) . In that case, he will have to wait for the performance of the promisor till the due date . He does so to take advantage of any act which makes the contract performable . THE WHOLE POINT TELLS THAT, PROMISEE MAY NOT END THE CONTRACT AND TREAT IT ALIVE