Oh.. I understood.. If work certified and work uncertified is given in the question
Then, work certified will be in value
And work uncertified will be in cost
Isn't so.?
Cost of work uncertified represents the cost of work which has been carried out by the contractor but not certified by the expert. It is always shown at cost price.
Value of work certified = Value of contract x work certified %