Forums
Back
Costing
In this sum , if we calculate % of work completed the ans is 46% . So the calculation for profit transfer to costing p&l will be 1/3 (NP) Ã? cash received/work certified. But sir solved in 90% work completed method. In the video he is saying , it is mentioned in the question but no information regarding this is mentioned in the question . Now which method i should follow
Answers (3)
KanakaMahaLaxmi Gunisetti
Plz read the question against U'll definitely understand:)
Again*...in the question they said the contract is going to complete by September 30,2021..