Why have we not taken value of output of process 1 while calculating cost p.u. of process 2?
Answers (3)
Thread Starter
Sagar KathuriaYes, but why haven't we considered it while calculating cost p.u. in WN 2
It is considered in 3,28,500 as the value of output of process 1 will become input for process 2. There is error in the values. It is 18000 not 1800. Please check