Doubt on adjustment number (4) - How labour efficiency decreased by 20% leads to 3.75 hrs

d7783e52-9679-477c-8af1-065328631883.jpg
746d4615-c894-4667-bb72-7793decc8929.jpg

Naren

Naren

CA Inter

90K+

18-Sep-21 12:40

685

Answers (1)

Best Answer

3/80% as 20% deficiency that means 3 hrs per unit is 80% efficiency