Standard vs Budgeted cost

Costing

What is the difference between standard cost and budgeted cost?


Mansha Tutlani

Mansha Tutlani

CA Final

555

13-Mar-22 20:09

2K+

Answers (3)

Standard costs are used in ideal conditions and situations. These are predetermined or planned costs. Budgets are made and used in diverse conditions and situations. These are based on past experience.


Yoga Vishnu

Standard costs are used in ideal conditions and situations. These are predetermined or planned costs. Budgets are made and used in diverse conditions and situations. These are based on past experience.

Yes, Standard cost indicates what the cost should be(benchmark) Whereas budgeted cost(estimated cost) indicates what the cost will be (based on past experience and adjusting past figure )


Thread Starter

Mansha Tutlani

Mansha Tutlani

CA Final

555

14-Mar-22 17:29

Standard Cost = Budget Cost for Actual Output (Actual Output * Standard Cost Per Unit) Budgeted Cost = Budget Cost for Budgeted Output (Budgeted Output * Standard Cost Per Unit)


Ravikumar Pandi

Ravikumar Pandi

CA Inter

2K+

15-Mar-22 11:49