Why they taken actual data for flexible budgeted ?? What is static budget?

25028665-f557-4018-a03c-bc2fba95f571.jpg
e78d5e2c-e398-444d-82d3-a66014ff3917.jpg

Devisree

Devisree

CMA Inter

0

22-Apr-24 18:05

55

Answers (3)

Best Answer

Static budget means a fixed budget. When preparing a flexible budget we take the actual number of units and re state all numbers. Fixed cost remains same irrespective of the level of activity. For this reason fixed cost is taken as appearing in static budget


Pranay Mehta

Pranay Mehta

Faculty

24-Apr-24 08:40

Static budget is like an Estimated budget so that's why they are taken Actual budget


RAJESH REDDY

RAJESH REDDY

CA Final

2K+

23-Apr-24 00:33

For some of the items like fixed overhead etc. They taken from static budget? Why?


Thread Starter

Devisree

Devisree

CMA Inter

0

23-Apr-24 07:15

May15 | 15% Off on ALL Courses